Unpriced bill of quantities
A bill of quantities (BoQ) is an important document prepared by a quantity surveyor (or cost consultant) which itemises the type, form and amount of material that will be required on a project, including quantities of labour and other items. Quantities may be measured in number, length, area, volume, weight or time and are known as ‘measured quantities’.
A BoQ may be priced, in that prices are given by suppliers for each item. The sort of considerations that might be considered when pricing work include current costs of materials, machinery hire and transport, wages, overhead expenses associated with administration and so on.
In contrast, an ‘unpriced bill’ is a BoQ that is essentially a template: it breaks down the work required on a project into exact tasks but has no measured quantity (or price) by each task. The information is arranged into a form that is suitable for direct pricing by a supplier, describing the individual items to be priced and the numbers, amounts or quantities of each required for the project.
It is up to the company tendering for the project to insert against each task what it will charge the client to complete that task. This priced bill of quantities constitutes the tenderer's offer. It is the unpriced bill of quantities, but with the tenderer’s rates, costs and totals added.
The preparation, by the client’s consultants, of an unpriced bill of quantities means all tendering contractors will be pricing the same quantities (rather than taking-off quantities from the drawings and specifications themselves), and so provides a fair and accurate system for tendering. It also makes it possible to compare both the overall price and individual items directly with other tenderers’ offers, allowing a detailed assessment of which aspects of a tender may offer good or poor value. This information can assist with tender negotiations.
[edit] Related articles on Designing Buildings Wiki
- Approximate bill of quantities.
- Approximate quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- New Rules of Measurement.
- NRM1.
- NRM2.
- NRM3.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Working up construction works.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Introduction to radon awareness
New technical information sheet published by CIOB.
Updated supplier guide can help electrical contractors engage with NHP.
CIAT confirm the winners of the 2026 architectural technology awards.
Government launches a one stop shop for flood preparedness.
Sir Edwin Lutyens: Britain's greatest architect? Book review.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.
Building safety levy for England
CIAT publish estimator tool for members.
Water sector faces a growing crisis that could slow the delivery of vital infrastructure.
Undervaluing our industrial past
Heritage value changes as taste for building styles changes.
Changing expectations around competence and compliance
New information sheet from CIAT.